Recommendation: Minimum of 4 Test Changeovers
Functional test
Local currency changeover and business processes after the changeover
Performance test (I)
Runtime determination using certain parameters
Performance test (II)
Runtime optimization using different parameter settings
Dress rehearsal
1-7 days before productive changeover with up-to-date productive data
optional: Check restart capability / the real thing
Familiarization with procedure if conversion terminates
SAP AG 1999
You should carry out at least 4 test changeovers before the productive changeover. You should use an up-to-date copy of the productive system for the functional test and dress rehearsal respectively. You should the same dataset for the performance tests, so that you can judge the effect of changing certain basic parameters accurately. To be on the safe side, test a worst case situation, such as termination of the conversion resulting from a power failure. You can thus familiarize yourself with the measures that need to be taken and can react more quickly and correctly should the real situation arise.