Recommendation: Minimum of 4 Test Changeovers
Functional test
Local currency changeover and business processes after the changeover

Performance test (I)
Runtime determination using certain parameters

Performance test (II)
Runtime optimization using different parameter settings

Dress rehearsal
1-7 days before productive changeover with up-to-date productive data

optional: Check restart capability / the real thing
Familiarization with procedure if conversion terminates
 SAP AG 1999

You should carry out at least 4 test changeovers before the productive changeover. You should use an up-to-date copy of the productive system for the functional test and dress rehearsal respectively. You should the same dataset for the performance tests, so that you can judge the effect of changing certain basic parameters accurately. To be on the safe side, test a worst case situation, such as termination of the conversion resulting from a power failure. You can thus familiarize yourself with the measures that need to be taken and can react more quickly and correctly should the real situation arise.

© SAP AG

CA990

1-11

Ještě nehodnoceno. Buďte první :-)
C: SELECT name, thumb, pages FROM 0_books WHERE nid = %d or nid = %d - SQL insert statement is invalid
C: SELECT name FROM 0_books WHERE thumb=1 and nid<>%d ORDER BY viewed DESC LIMIT 66 - SQL insert statement is invalid